Midlands Water Scheme Construction Update 19 December 2012


Since the commencement of construction Fulton Hogan has upgraded all access roads, cleared about 24km of corridor from Lake Sorell to the Lake River, commenced delivery and installation of high pressure pipe. Zezt has produced about 32 km of poly pipe and have been delivering to site since the start of November. Hazell Bros have largely completed the installation of the large DN 1000mm diameter HDPE pipe from Floods Creek Dam to the pump station, are progressing well laying the pipe along the Isis branch line and have commence work on mainline 1 (Floods Creek to the Midlands Highway).

Download the document here

Join our mailing list for the latest news and information.